Date: 05.11.2020.
BUILDING: Residential – business building
INVESTOR: “FINEST” d.o.o Trebinje
Works are underway on the construction of a residential and business building of floors S + VP + 5 + Pe in the Trebinje settlement of Zasad polje, on plots marked as cp no. no. 2291/58 (according to the new operetta) KO Trebinje 1.
The building is divided into two lamellae L1 and L2, basically “L” shaped.
The basement floor is intended for a garage, and the residential units are designed on higher floors, VP + 5 + Pe.
Earthworks on the excavation of the foundation pit of lamella 1 and lamella2 have been completed.
Execution in progress:
reinforced concrete works, which include reinforcing, carpentry and concrete works on the positions of pillars, walls, elevator shafts, stairs, beams and mezzanine structures.
masonry work, masonry of facade walls d = 25 cm and partition walls d = 12 cm.
works on electrical installations
works on water supply and sewerage
Slat 1:
basement: – reinforced concrete works and masonry works have been completed
high ground floor: -reinforced concrete works have been completed
-masonry works have been completed, masonry of facade walls d = 25 cm, partition walls between apartments and partition walls d = 12 cm.
– completed machine plastering of walls and ceilings
– distribution of water and sewage completed
– Divorce wiring completed
– plaster works are in progress
first floor: – reinforced concrete works have been completed
– masonry work completed, masonry of facade walls d = 25 cm, partition walls between apartments of partition walls d = 12 cm
– machine plastering is in progress
– distribution of water and sewage installations completed
– divorce electrical installation completed
second floor: – reinforced concrete works have been completed
– masonry works have been completed, masonry of facade walls d = 25 cm, partition walls between apartments of partition walls d = 12 cm.
– works on the distribution of water and sewage installations are in progress
– works on the distribution of electrical installations are in progress
third floor: – reinforced concrete works have been completed,
– masonry works are in progress
fourth floor:
– reinforced concrete works have been completed
– completed dismantling of beam and slab formwork and cleaned
fifth floor: – dismantling of the slab
withdrawn floor: – reinforced concrete works are in progress
PVC facade openings were installed on the high ground floor, first and second floor
Slat 2:
basement: – reinforced concrete works and masonry works have been completed
high ground floor: -reinforced concrete works have been completed.
– masonry works have been completed, masonry of facade walls d = 25 cm, partition walls between apartments of partition walls d = 12 cm.
– completed machine plastering of walls and ceilings
– distribution of water and sewage installations completed
– divorce electrical installation completed
– plaster works are in progress
first floor: – reinforced concrete works have been completed,
– masonry works have been completed, masonry of facade walls d = 25 cm, partition walls between apartments and partition walls d = 12 cm.
– distribution of water and sewage installations completed
– divorce electrical installation completed
second floor: – reinforced concrete works have been completed
– masonry works have been completed, masonry of facade walls d = 25 cm, partition walls between apartments and partition walls d = 12 cm.
– works on the distribution of water and sewage installations are in progress
– works on the distribution of electrical installations are in progress
third floor: – reinforced concrete works have been completed,
– masonry work completed
– works on the distribution of water and sewage installations are in progress
– works on the distribution of electrical installations are in progress
fourth floor: – reinforced concrete works have been completed
– masonry work in progress
fifth floor: – completed reinforced concrete works
– dismantling of beam and slab formwork and cleaning
withdrawn floor: – reinforced concrete works in progress
PVC facade openings were installed on the high ground floor, first and second floor
During the execution of reinforced concrete works, works on distribution of electrical installations and works on distribution of water and sewerage are performed at the same time.
“FINEST” d.o.o. Trebinje