Dynamics on the construction of the first facility in SPK “Centar 2”

nov-2020

Date: 05.11.2020.

BUILDING: Residential – business building

INVESTOR: “FINEST” d.o.o Trebinje

Works are underway on the construction of a residential and business building of floors S + VP + 5 + Pe in the Trebinje settlement of Zasad polje, on plots marked as cp no. no. 2291/58 (according to the new operetta) KO Trebinje 1.

The building is divided into two lamellae L1 and L2, basically “L” shaped.

The basement floor is intended for a garage, and the residential units are designed on higher floors, VP + 5 + Pe.

Earthworks on the excavation of the foundation pit of lamella 1 and lamella2 have been completed.

Execution in progress:

reinforced concrete works, which include reinforcing, carpentry and concrete works on the positions of pillars, walls, elevator shafts, stairs, beams and mezzanine structures.
masonry work, masonry of facade walls d = 25 cm and partition walls d = 12 cm.
works on electrical installations
works on water supply and sewerage

Slat 1:

basement: – reinforced concrete works and masonry works have been completed
high ground floor: -reinforced concrete works have been completed

-masonry works have been completed, masonry of facade walls d = 25 cm, partition walls between apartments and partition walls d = 12 cm.

– completed machine plastering of walls and ceilings

– distribution of water and sewage completed

– Divorce wiring completed

– plaster works are in progress

first floor: – reinforced concrete works have been completed

– masonry work completed, masonry of facade walls d = 25 cm, partition walls between apartments of partition walls d = 12 cm

– machine plastering is in progress

– distribution of water and sewage installations completed

– divorce electrical installation completed

second floor: – reinforced concrete works have been completed

– masonry works have been completed, masonry of facade walls d = 25 cm, partition walls between apartments of partition walls d = 12 cm.

– works on the distribution of water and sewage installations are in progress

– works on the distribution of electrical installations are in progress

third floor: – reinforced concrete works have been completed,

– masonry works are in progress

fourth floor:

– reinforced concrete works have been completed

– completed dismantling of beam and slab formwork and cleaned

fifth floor: – dismantling of the slab
withdrawn floor: – reinforced concrete works are in progress
PVC facade openings were installed on the high ground floor, first and second floor

Slat 2:

basement: – reinforced concrete works and masonry works have been completed
high ground floor: -reinforced concrete works have been completed.

– masonry works have been completed, masonry of facade walls d = 25 cm, partition walls between apartments of partition walls d = 12 cm.

– completed machine plastering of walls and ceilings

– distribution of water and sewage installations completed

– divorce electrical installation completed

– plaster works are in progress

first floor: – reinforced concrete works have been completed,

– masonry works have been completed, masonry of facade walls d = 25 cm, partition walls between apartments and partition walls d = 12 cm.

– distribution of water and sewage installations completed

– divorce electrical installation completed

second floor: – reinforced concrete works have been completed

– masonry works have been completed, masonry of facade walls d = 25 cm, partition walls between apartments and partition walls d = 12 cm.

– works on the distribution of water and sewage installations are in progress

– works on the distribution of electrical installations are in progress

third floor: – reinforced concrete works have been completed,

– masonry work completed

– works on the distribution of water and sewage installations are in progress

– works on the distribution of electrical installations are in progress

fourth floor: – reinforced concrete works have been completed

– masonry work in progress

fifth floor: – completed reinforced concrete works

– dismantling of beam and slab formwork and cleaning

withdrawn floor: – reinforced concrete works in progress
PVC facade openings were installed on the high ground floor, first and second floor

During the execution of reinforced concrete works, works on distribution of electrical installations and works on distribution of water and sewerage are performed at the same time.

“FINEST” d.o.o. Trebinje