Good dynamics of works on the construction of the first facility in SPK “Centar2”

centar2

Works are underway on the construction of a residential and business building of floors S + VP + 5 + Pe in the Trebinje settlement of Zasad polje, on plots marked as cp no. no. 2291/58 (according to the new operetta) KO Trebinje 1.

The building is divided into two lamellae L1 and L2, basically “L” shaped.

The basement floor is intended for a garage, and the residential units are designed on higher floors, VP + 5 + Pe.

Earthworks on the excavation of the foundation pit of lamella 1 and lamella2 have been completed.

Execution in progress:

  • reinforced concrete works, which include reinforcing, carpentry and concrete works on the positions of pillars, walls,elevator shafts, stairs, beams and mezzanine structures.
  • masonry work, masonry of facade walls d = 25 cm and partition walls d = 12 cm.
  • works on electrical installations
  • works on water supply and sewerage

Lamell 1:

  • basement: – reinforced concrete works and masonry works have been completed
  • high ground floor: -reinforced concrete works have been completed
    -masonry works have been completed, masonry of facade walls d = 25 cm, partition walls between apartments and partition walls d = 12 cm.
  • first floor: – reinforced concrete works have been completed
    – masonry works have been completed, masonry of facade walls d = 25 cm, partition walls between apartments of partition walls d = 12 cm.
  • second floor: – reinforced concrete works have been completed,
    – masonry works have been completed, masonry of facade walls d = 25 cm, partition walls between apartments of partition walls d = 12 cm.
  • third floor: – reinforced concrete works have been completed,
  • fourth floor: – reinforced concrete works have been completed
  • PVC facade openings were installed on the high ground floor

Lamell 2:

  • basement: – reinforced concrete works and masonry works have been completed
  • high ground floor: -reinforced concrete works have been completed.
    – masonry works have been completed, masonry of facade walls d = 25 cm, partition walls between apartments of partition walls d = 12 cm.
  • first floor: – reinforced concrete works have been completed,
    – Masonry works have been completed, masonry of facade walls d = 25 cm, partition walls between apartments and partition walls d = 12 cm.
  • second floor: – reinforced concrete works have been completed
    – Masonry works have been completed, masonry of facade walls d = 25 cm, partition walls between apartments and partition walls d = 12 cm.
  • third floor: – reinforced concrete works have been completed,
  • fourth floor: – reinforced concrete works have been completed
  • fifth floor: reinforced concrete works are in progress
    PVC facade openings were installed on the high ground floor and the first floor

During the execution of reinforced concrete works, works on distribution of electrical installations and works on distribution of water and sewerage are performed at the same time.